Project Milestone Schedule | ||||
Milestone | From Appointment Date | Contractual Dates as per CA | Target/Ach. Dates | Milestone Event |
MS-1 | 150 days | 29-03-2023 | 20% of the Physical & Financial Progress. | |
MS-2 | 330 days | 25-09-2023 | 35% of the Physical & Financial Progress. | |
MS-3 | 510 days | 23-03-2024 | 75% of the Physical & Financial Progress. | Schedule Completion Days | 730 days | 29-10-2024 | Shall have completed the Project in accordance with this Agreement. |